A global green energy company, is committed to producing green, fossil-free hydrogen from 100% renewable resources. The company wishes to develop a green energy project in Kenya aimed at:
- supplying electricity from renewable resources, as well as producing green hydrogen and ammonia for domestic and international markets;
- using the existing infrastructure and electricity transmission grid and developing a storage and export facility for finished products.
Seureca performed a pre-feasibility study covering water access and the infrastructure required by the hydrogen and ammonia production facility.
Our solution
The missions entrusted to Seureca concern:
- verifying the availability of the resource and infrastructure required to implement this project;
- estimating costs (CAPEX/OPEX);
- drawing up recommendations and technical specifications to define and optimise the design of the water treatment process and implementation schedule;
- defining the approvals and compliance required to build and manage water supply and wastewater discharge from the production facility;
- providing recommendations for waste management: dewatering and disposing sludge produced by water treatment plants;
- taking safety into account in process design, including risk identification and management measures;
- the constructability study integrating logistics and a preliminary schedule.