To reduce the drinking water production deficit in the city and surroundings of Yaounde, the Cameroonian government launched a project to supply drinking water from the Sanaga River. The principal infrastructures of this project will be designed to produce 300,000 m³ of water per day, expandable to 400,000 m³ per day
This project is financed by the Exim Bank of China; the design and construction were commissioned to the SINOMACH company.
Our solution
Since September of 2015 Seureca is in charge of the project management on behalf of the Cameroonian government, namely:
- Providing legal, financial, and contractual assistance;
- Checking both the design documents and the implementation documents;
- Supervising the execution of the works;
- Assisting with the reception, as well as staff-training operations.
To support the government in the implementation of one of the largest on-going drinking water projects in Africa, Seureca has set up a multidisciplinary and multicultural team aimed to:
- ensure that the works are executed in compliance with current professional standards;
- respect the deadlines and budgets of the initial construction contract.